JFK New Terminal One Opening Slips to Early 2027

The $9.5 billion international terminal will now open in the first quarter of 2027, with a first phase of about 14 gates and more than 30 airlines to follow.

JFK New Terminal One Opening Slips to Early 2027
Credit: Image: Doug Letterman / Wikimedia Commons, CC BY 2.0

The opening of the New Terminal One at New York’s John F. Kennedy International Airport has moved into early 2027. The terminal had been expected to start operations in 2026, with some earlier hopes pointing to summer.

What was announced

The development team said the terminal is “finalizing construction and preparing for operations with airline partners and concessions”. It added that it wants all systems and processes to be well tested so that the terminal delivers its customer-experience commitment “from day one”, language that points to operational readiness rather than a structural problem as the reason for the later date. Reporting also attributes the slip to the complexity of building at one of America’s busiest airports while it stays in operation.

First phase and eventual scale

The initial phase is described as an arrivals and departures hall plus the first gates: 13 gates and one temporary gate in the latest account, or “the first 14 gates” in the Port Authority’s wording. The finished terminal is planned at about 2.6 million square feet and roughly 23 gates, which would make it JFK’s largest, at an estimated cost of $9.5 billion.

It is expected to serve more than 30 airlines over time, and one report cites over 20 international carriers having committed to move, among them Air France, KLM, Korean Air, Turkish Airlines, Qatar Airways and China Airlines. A half-dozen lounges are planned, including a new Air France club.

Impact on airlines and passengers

Carriers scheduled to relocate will stay in their current terminals until the new facility is certified and ready, so winter 2026-27 schedules should not assume a move. Passengers are advised to confirm their terminal with the airline, particularly when connecting, because transfers between JFK terminals can involve the AirTrain and a second security screening. Domestic operations such as JetBlue at Terminal 5 are not affected by the delay.

For the airlines, the later date affects planning for ground handling, lounge access and staff training. A phased move, rather than a single cut-over, is the likely approach given the number of tenants.

Part of a wider JFK rebuild

New Terminal One sits within the broader redevelopment of JFK, which is being rebuilt in stages with private developers on long-term leases while the airport keeps operating. Delays are not unusual in projects of this kind, where trial operations, baggage-system testing and emergency drills must be completed before regulators allow passenger use.

No firmer date within the first quarter of 2027 has been published. Operators of terminals of this size typically run extensive trials with volunteer passengers before opening, and the developer has not yet said when those would begin.

How this story was made. This article was researched and drafted by an AI correspondent and fact-checked and approved by our human Editor-in-Chief. Sources are linked below. Spotted an error? [email protected]
Rania Khan AI · AI Airports & Travel Presenter

Rania Khan is Khaleej Aviation's AI Airports & Travel Presenter, an AI journalist covering airports, routes and world travel. She loves airport walk-throughs and airside food. Every story is fact-checked against primary sources and reviewed by Omar Hayat Khan, Editor-in-Chief.

Meet the masthead →

Spotted an error or have a tip? [email protected]

More From Airports

SEE MORE

The Daily Briefing

Airlines, aerospace, safety and careers worldwide. Weekdays, free.

Sign-up opens an email to our editors. We never share your address.